This is what a money pit looks like- literally. Zoom in for the full effect!
This hole is roughly four feet deeper than the bottom of the lowest part of the back barn. The forms you see wrapped in tarps will be the footings that will hold the new foundation wall that spans the width of the barn, separates the lower level of the main barn from the lower level under the back barn (roughly 5 feet difference), and keeps the barn from sliding down the hill. This wall will be the most important piece of saving this old barn for future generations. We decided to use poured concrete due to the difficulty in getting machinery under the back barn to stack stone, cost, and no one will ever see it anyway. It will also provide structure for the most critical piece of drainage in this entire project: funneling away the underground stream that comes from the spring under our ell.
This all began last week when John and Seth (our timber framers) dismantled the wall separating the barn basement to the lower level of the back barn. In doing so, a lot more rot and old patches were uncovered. The intent was to install temporary 6″ x 8″ beams that would carry the load of the entire center of the barn, which would allow digging across the entire width of the barn. You can see in the first image below, the immense weight these beams are carrying. We were saying prayers for the safety of the crew the entire time they were under there.
While dismantling the siding for access to install the beams, this little treasure was exposed- this is called a “scarf joint”, and is used for joining two beams longitudinally.
Once the barn was adequately supported, Mike’s team (excavation, foundation and boulders) began digging out above the wall so that they could get the baby excavator under the barn to dig the depth for the footings.
The new wall will sit just under the ends of the beams you see in the last image above, and after the drainage is installed and the pit is backfilled, this area from the new lower wall forward to the two (nearest) posts shown in the second from the last image above, will be leveled off. We’ll (eventually) pour a concrete pad, and this area will be our “garage” where we can jack up and work on cars, weld, grind, and anything else we can’t do on the wood plank floor in the barn upstairs. We’ll put up partition walls on both sides, build an 8-9′ sliding door for entry, and install a couple of windows on the south side (opposite the door) for natural light. The area further forward will be for storage, and we’ll leave that with a gravel floor. We’re thinking we’ll install tubing in the concrete floor should we later decide to add a small boiler for in-floor radiant heat. Our contractor thinks we’ll end up with just over 7′ of head room to the beams.
While the foundation guys were digging underneath, the timber framers were working on the front sill and door threshold. They installed pressure-treated planks over the sill beams for protection, then the front was backfilled and the new driveway ramp was installed. Next spring they’ll re-install the granite threshold, which will give us a nice, gentle entry into the barn rather than the janky collection of planks we used to use to get the cars inside (and the MG bottomed out anyway).
After Jenny and I took out the loft floor in the first two bays (saving all the lumber possible), they also took out the janky half wall/too-small-post, and replaced it with an 8″ x 8″ hemlock post. It was fun watching it get winched up into place.
We also worked on painting up a couple more rooms; the mudroom and parlor. The parlor was previously painted salmon pink with reproduction stencils from the second owner of the house (Moses Eaton Jr.) to match a panel left intact with his original stencils from the mid-19th century. Since we are taking the house back to the original owner/builder (Daniel and Abigail Warren), and the plaster in this room is failing, we went ahead and painted something more appropriate (“High Tea” with “Perfect Taupe” trim), but left the single panel of Moses’ original stencils. We decided on a buttercream yellow for the mudroom, with the “Perfect Taupe” trim. Keep in mind, “painting” in this old a home usually means stripping and cleaning layers of paint off of hinges and hardware, planing cabinet door edges to remove layers of paint that keep them from closing, priming just about everything, and changing out the often painted (maybe more than once) outlets and switches, along with the cover plates.
In the mudroom, we’re working on making a plank (that we found in the barn) with antique forged nails we’ll hang above the bench to use to hang coats.
We also ran back to the auction in Vermont and picked up this antique harvest table, shaker chairs, and Windsor bench. Note that the table top is a single, solid board (we think cherry). It’s crazy that no one wants this “old stuff”.
That’s it for now- it’s going to be a crazy week coming up! The contractor will be starting on Monday to replace the granite sill under the front door of the house, along with some other structural work, and install the new, antique, floorboards in the hearth room. Not sure where everyone will park, as most of the yard is filled with staging of heavy equipment, piles of various size rocks, boulders, gravel, and dirt, as well as the barn contractor’s team’s trucks and trailers, etc.
Stay tuned!